Queensbridge House Development Newsletter

August 2021: Summary of work
Works on the South Zone have been progressing well. All internal first fix works have now been completed. Internal final fix, finishes and decorations are currently being completed within the last public areas and apartments. External stone cladding installation at lower levels are ongoing. All scaffolding has now been removed. Additionally, the new river walkway stone paving and finishes are ongoing. Porte cochere works are also ongoing.

In the Central Zone, all internal first fix works have now been completed.Internal final fix, finishes and decorations are close to completion.Guestrooms have now been completed, with loose furniture now going in.External stone cladding installation are still ongoing.In the North Zone, all internal first fix works have been completed. Internal final fix, finishes and decorations are currently being completed within the last public areas and apartments. External stone cladding installation at lower levels are ongoing. All scaffolding has now been removed.Guestrooms have been completed with loose furniture now going in.

Upcoming Works
Over the next two months, the following works are set to be progressed:
• Complete cladding installation in all areas
• Complete final internal service installation and commissioning in all areas
• Complete internal finishes, decoration and fit out works in all areas.

Updated contact details
If you have an urgent query about works
on site, please contact:
Sailesh Vekaria
Contracts Manager, Vascroft Contractors Ltd
T 07734 845 334

Out of hours security
Sicuro Security
T 0800 9991 888
For all comments or queries about the project,
including our programme of works, please contact Four Communications via: